26 Jul 2022

Lobby expansion, pedestrian tunnel open in phase one of $608 million CLT update

Charlotte Douglas International Airport (CLT) opened portions of the terminal lobby expansion’s west side Wednesday morning, the airport reported. It is the first phase to debut to passengers.

The addition is a sneak peek of the overall look of the project that will have large, picturesque windows, terrazzo flooring throughout, bright blue tiles framing the entrances/exits and architectural-detailed ceilings.

“This is a big moment for us,” CLT Chief Operating Officer Jack Christine said. “Opening this piece of the project allows us to not only continue finishing the expansion of the east side of the lobby, but also allows us to start the renovation phases of the project and stay on target to complete the entire [terminal lobby expansion] in 2025.”

The expansion’s west side provides:

  • Approximately 90,000 square feet of additional circulation space
  • Access to the west subterranean walkway. Located on the Hourly Deck’s first floor, the tunnel offers a traffic-free, covered walking path from the deck to the terminal.
  • Three new art pieces – “Meridian” by Danielle Roney, “Carolina Moon” by Scott Parsons and “Restless Sky” by Catherine Widgery
  • Twenty of CLT’s signature white rocking chairs in Arrivals/Baggage Claim
  • Thirty new Flight Information Display (FIDS) monitors

The entire lobby expansion will wrap up in 2025. Customer amenities will include modern ticket counters, eight original artworks, charging stations, three large security checkpoints and five pre-security concession spaces. The $608 million signature project will transform the airport’s entrance with 366,000 square feet of new and renovated space, along with a 146,000-square-foot stunning canopy that will begin construction in September.

“The completed terminal lobby expansion will be spectacular,” Christine said. “It will be modern, spacious, filled with natural light and worth the wait. Our passengers will definitely be impressed.”

The terminal lobby expansion is part of Destination CLT, the airport’s $3.1 billion capital investment program that includes concourse renovations and expansion of CLT’s roadways, curb front, the airfield and terminal.

As passengers approach the airport, they can use the following three new entrances/exits:

  • Door 2 on Arrivals/Baggage Claim level
  • Doors 1 and 2 on the Departures/Ticketing level 

Upon entering the terminal’s upper or lower levels, ticket counters, security checkpoints and luggage carousels are not immediately visible. Signage has been installed to point customers in the right direction. Airport employees are stationed in Arrivals/Baggage Claim and Departures/Ticketing this week to assist with wayfinding as well.

Related Content

06 Jan 2025 Company to invest $93M, add quarry in Chester County

A company with a presence in South Carolina will create dozens of jobs with the expansion of its quarry operations in Chester County. Luck Companies provides crushed stone aggregates and environmental performance products. The company is adding new quarry sites in four South Carolina counties, including Chester County. Chester County… Read More

06 Jan 2025 Charlotte airport has $37B economic impact, new analysis shows

Newly released data reinforces how essential aviation is to the Charlotte Region’s economy. In its biennial report published in January, the North Carolina Department of Transportation’s Division of Aviation highlighted how North Carolina’s airports are contributing to the state’s success. The 72 airports in the Tar Heel State transported… Read More